Case 25 · Public money
100 smart cities. One finished on time
Launched 25 Jun 2015
Deadline moved five times
4,069 days since Recorded outcome: Deadline moved five times.
What happened
Claim against record
What the government said
The ministry's position is that the mission was never meant to transform whole cities: it was deliberately an area-based development model of retrofitting, redevelopment and greenfield work inside a defined area, plus one pan-city digital initiative, intended to create a replicable template. On that yardstick it reports 97% project completion, 99% of the central share claimed and 98% of released funds used as of March 2026, and cites a NITI Aayog evaluation of September 2025 finding the mission demonstrated strong relevance to India's urban needs.
What the record shows
Deadline moved five times
The deadline moved from 2019-20 to June 2023, then June 2024, then March 2025, then June 2025, then December 2025. The Parliamentary Standing Committee on Housing and Urban Affairs found in February 2024 that 400 projects worth ₹22,814 crore would miss even that, and that the ministry's answer was that states would have to finish them at their own cost — prompting the committee to observe that the ministry's role 'should not be confined to transfer of their share'. Only 6% of projects were financed through public-private partnership against a targeted 21%, which is the mission's financing model failing rather than lagging. Nearly a year after official closure, 280 projects worth ₹8,652 crore were still under implementation, and the unfinished work is the expensive work: ₹29 crore average for what is still running against ₹20.1 crore for what is done.
Contested / alleged
What accountability should have looked like
Ministers and office-holders responsible
- Owns the mission; five deadline extensions, unfinished projects passed to statesMinistry of Housing and Urban Affairs
Naming who held the portfolio is a matter of public record. It is not by itself a finding of personal responsibility for any death or any rupee.
Sources
T1 primary record · T2 reporting · T3 partisan
- T2 400 projects to miss the deadline ↗ Archived copy
- T2 Mission set to end 31 March 2025 ↗ Archived copy
- T2 Rajya Sabha reply: status to Mar 2026 ↗ Archived copy
- T2 A decade on, the mission still lags ↗ Archived copy
Ask them officially. File an RTI Know a better source? Add one
Cite or export this case
Citizens' Accountability Ledger, "100 smart cities. One finished on time" (Launched 25 Jun 2015), case-62. https://whoisresponsible.xyz/case/case-62/
JSON for this case The whole ledger as CSV
Quote the case id rather than the number on the card. The id never changes; the number shifts whenever an older case is added ahead of this one.